Department of Infrastructure, Transport, Regional Development, Communications, Sport and the Arts
Documents relating to the ACIL Allen verification and assurance of scope, design, delivery and cost assurance of Inland Rail
Summary
AI-generatedWritten by Claude Haiku 5.5 from the extracted text on 21 Oct 2026. It can miss or misread redacted and scanned pages. Check the source before relying on it.
This FOI release is the final report by ACIL Allen on its independent verification and assurance of the Inland Rail Project's scope, design, delivery schedule and cost estimation, commissioned by the Department in late 2024. It assesses the updated schedule and cost estimate that Inland Rail Pty Ltd provided in March 2025, current as of December 2024, covering Target and Stretch scenarios. The report focuses on the Target scenario, which assumes a full IRP commencement date of 30 June 2025. Key themes include schedule duration outliers across land acquisition, approvals, design stages and construction, and a Multicriteria Assessment of Section complexity. It also covers contingency adequacy, with the P90 allowance for three Northern Sections at 23.2 per cent, described as low for Class 4 estimates, and the Gowrie to Kagaru estimate, which relies on a preferred PPP bid rather than a bottom-up assessment. Several value engineering opportunities for Northern Sections may not yet be reflected in design and cost.
Document text
74,234 characters extracted from 113 pages
The document text opens on its own page.