NOPS
NOPSEMA
Date not published
F246-05
2 pages
PDF
This email thread documents Woodside Energy's submission to NOPSEMA regarding the Scarborough environment plans assessment in July 2023. Woodside requested that NOPSEMA consider Woodside's response to the Environmental Defenders Office (dated 3 July 2023) when making regulatory…
-
NOPS
NOPSEMA
Date not published
F246-04
5 pages
PDF
Woodside Energy submitted correspondence to NOPSEMA on 4 July 2023 requesting that its response letter to the Environmental Defenders Office (dated 3 July 2023) be considered during NOPSEMA's assessment of multiple Scarborough environment plans. The four environment plans under…
-
NOPS
NOPSEMA
Date not published
F246-03
2 pages
PDF
On 22 June 2023, NOPSEMA notified Woodside Energy Scarborough Pty Ltd that it was unable to complete its assessment of the Scarborough 4D B1 Marine Seismic Survey environment plan within the standard 30-day review period. The operator had submitted the plan (Revision 7) on 2…
-
NOPS
NOPSEMA
Date not published
F246-02
2 pages
PDF
Woodside Energy submitted Revision 7 of its Scarborough 4D Multi-Sensor Seismic (MSS) Environment Plan to NOPSEMA on 12 June 2023. The submission corrected and updated several sections, including removal of non-adjacent Native Title claims and determinations from Table 4-17…
-
NOPS
NOPSEMA
Date not published
F246-01
11 pages
PDF
NOPSEMA rejected Woodside's environment plan for the Scarborough 4D B1 marine seismic survey because the plan inadequately described cultural heritage features and relied improperly on an independent heritage report commissioned by NOPSEMA rather than Woodside's own…
-
NOPS
NOPSEMA
Date not published
F329-02
1 page
PDF
This handwritten meeting note records a October 2025 Teams discussion between NOPSEMA and the Department of Climate Change, Energy, Environment and Water (DCCEEW) regarding hazardous waste management for offshore petroleum operations. The meeting addressed Santos' proposed…
-
NOPS
NOPSEMA
Date not published
F329-01
1 page
PDF
These are handwritten meeting notes from a NOPSEMA staff member documenting a 30 July 2025 discussion with the Department of Climate Change, Energy, Environment and Water (DCCEEW) regarding Santos' Environment Plan (EP). The meeting covered Basel Convention implementation…
-
NOPS
NOPSEMA
Date not published
F332-01
19 pages
PDF
NOPSEMA Investigation IVT-12396 examined alleged breaches of petroleum safety zones (PSZs) at Woodside Energy Limited's Griffin and Nganhurra Riser Turret Mooring facilities. The investigation, commenced May 13, 2023, involved the Rainbow Warrior vessel and Greenpeace Australia…
-
NOPS
NOPSEMA
Date not published
F338-01
11 pages
PDF
NOPSEMA initiated a Level 2 investigation (IVT14417) into a complaint by Eastern Maar Aboriginal Corporation regarding Woodside Energy's handling of plastic saddles and associated materials lost to the marine environment during Minerva decommissioning operations. The…
-
NOPS
NOPSEMA
Date not published
F051
2 pages
PDF
NOPSEMA's investigation summary documents a hydrocarbon release incident at Woodside Energy's CWLH OKHA FPSO on 7 October 2011. A fire and gas detection system activated following a small gas release in a pressure vessel breaker, triggering emergency response procedures and…
-
NOPS
NOPSEMA
Date not published
F058
1 page
PDF
In September 2012, Transocean submitted an initial incident notification to NOPSEMA regarding a dangerous occurrence at the Jack Bates offshore facility. The submission, made via email on 27 September 2012, indicated a potential fatality and was accompanied by a formal…
-
NOPS
NOPSEMA
Date not published
F114
2 pages
PDF
This FOI disclosure contains 73 redacted incident and enforcement reports from NOPSEMA relating to the Ichthys Development Project operated by INPEX Ichthys Pty Ltd, covering two floating production facilities: Ichthys Explorer and Ichthys Venturer. The documents include…
-
NOPS
NOPSEMA
Date not published
F184
No document available
No summary: no document is available for this release
-
NOPS
NOPSEMA
Date not published
F195
4 pages
PDF
NOPSEMA internal correspondence from July 2019 regarding urgent safety concerns at the Northern Endeavour NOGA floating production, storage and offloading (FPSO) facility. Two corrosion-related dropped object incidents were reported within days of each other: Notification 6019…
-
NOPS
NOPSEMA
Date not published
F196
1 page
PDF
NOPSEMA's OHS Regulatory Specialist sent a memo on 6 July 2019 notifying colleagues of an upcoming meeting at UPS offices to discuss dropped object incidents involving the Northern Endeavour facility. The memo indicates two separate dropped object notifications would be…
-
NOPS
NOPSEMA
Date not published
F198
4 pages
PDF
Santos presented to NOPSEMA on 3 February 2023 regarding its Gas Export Pipeline (GEP) project, covering installation plans, proposed environmental surveys, and stakeholder consultation. Santos' Environment Plan (Revision 3), accepted in March 2020 and expiring March 2025…
-
NOPS
NOPSEMA
Date not published
F201
3 pages
PDF
This email thread from May 2019 involves NOPSEMA staff discussing regulatory issues related to the Northern Endeavour facility and the Laminaria and Corallina offshore fields. The correspondence addresses whether relocating the Northern Endeavour within Australian jurisdiction…
-
NOPS
NOPSEMA
Date not published
F202
4 pages
PDF
NOPSEMA issued General Direction No. 1897 to Enfield riser turret mooring (RTM) registered holders requiring fortnightly monitoring and reporting of the Nganhurra RTM through decommissioning. As of 17 March 2023, the RTM remained afloat with a draft of 75.8 metres, navigation…
-
NOPS
NOPSEMA
Date not published
F205
5 pages
PDF
Santos submitted its 16th weekly progress report to NOPSEMA on 4 May 2023 in response to a General Direction issued 13 January 2023 under section 574 of the Offshore Petroleum and Greenhouse Gas Storage Act 2006. The Direction, issued to Santos NA Barossa Pty Ltd, SK E&S…
-
NOPS
NOPSEMA
Date not published
F207
1 page
PDF
Woodside Energy reported a dropped objects incident during drilling and completions operations at the Persephone field in September 2016. On 14 September, a fairlead pin and grating fell to the seabed from the Ocean Apex MODU during anchor pretensioning operations. The incident…