Woodside Energy Ltd notified NOPSEMA of a dangerous occurrence at the Vincent facility on 18 July 2022 involving failure of a process control module (PCM) during shunt trip testing. The electrical failure occurred when device 64-XS-4055 failed to trip non-Ex loads in the…
-
NOPS
NOPSEMA
Date not published
F233-08
5 pages
PDF
Woodside Energy Ltd reported a notifiable incident (NTF11645) on 14 July 2022 at the Vincent offshore facility in Western Australia involving two safety-critical valves that failed to meet performance standards during annual emergency shutdown (ESD) testing. One valve (Inlet…
-
NOPS
NOPSEMA
Date not published
F233-07
5 pages
PDF
Woodside Energy Ltd notified NOPSEMA of a dangerous occurrence on 14 July 2022 involving significant corrosion discovered in a high-pressure gas compressor on the Vincent facility in Western Australia. During routine inspection of a 50mm suction line, corrosion was identified at…
-
NOPS
NOPSEMA
Date not published
F233-06
5 pages
PDF
Woodside Energy Ltd reported a notifiable incident (NTF11640) on 12 July 2022 involving damage to the main hoist rope on the midships crane of the CWLH OKHA FPSO in Western Australian waters. During a routine weekly inspection, the rope showed apparent outer layer damage…
-
NOPS
NOPSEMA
Date not published
F233-05
3 pages
PDF
Woodside Energy Ltd notified NOPSEMA of a non-work-related medical incident aboard the CWLH OKHA FPSO on 12 July 2022. A crew member presented with a headache, disorientation, and memory loss and was medevaced to Karratha Health Campus on advice from the facility's medical…
-
NOPS
NOPSEMA
Date not published
F233-04
4 pages
PDF
Woodside Energy Ltd notified NOPSEMA of a notifiable incident (NTF11628) at the Vincent offshore facility on 10 July 2022, when a ultraviolet flame detector in the engine room unexpectedly activated, triggering a general alarm and personnel muster. No fire, damage, or…
-
NOPS
NOPSEMA
Date not published
F233-03
4 pages
PDF
Woodside Energy Ltd notified NOPSEMA on 10 July 2022 of a dangerous occurrence at the Vincent offshore facility in Western Australia involving a failed quick closing valve in the engine room. During routine six-monthly function testing, a pneumatic ram on the quick closing valve…
-
NOPS
NOPSEMA
Date not published
F233-02
4 pages
PDF
Woodside Energy Global notified NOPSEMA of a dangerous occurrence at its Pyrenees offshore facility in Western Australia on 1 July 2022, involving a failed level switch on the main pressure-vacuum (PV) breaker during routine function testing on 30 June 2022. The switch, designed…
-
NOPS
NOPSEMA
Date not published
F233-01
4 pages
PDF
Woodside Energy Global reported a notifiable incident (NTF11607) at the Pyrenees facility in Western Australia on 1 July 2022 involving integrity failure of a chemical bund. A 50mm pipe stub that penetrated the bund floor corroded and disconnected, compromising the bund's…
-
NOPS
NOPSEMA
Date not published
F246-11
6 pages
PDF
NOPSEMA accepted Woodside Energy's Scarborough 4D B1 Marine Seismic Survey environment plan with conditions on 31 July 2023, following a resubmission on 2 June 2023. Despite the resubmission, NOPSEMA remained unsatisfied that the plan met specific regulatory criteria under the…
-
NOPS
NOPSEMA
Date not published
F246-10
8 pages
PDF
In July 2023, NOPSEMA engaged with Woodside Energy regarding draft conditions for the Scarborough 4D Marine Seismic Survey Environment Plan. Internal email correspondence from July 25-26, 2023 shows NOPSEMA staff requesting Woodside's comments on proposed condition amendments…
-
NOPS
NOPSEMA
Date not published
F246-09
6 pages
PDF
NOPSEMA correspondence from July 2023 documents the approval process for Woodside Energy's Scarborough 4D Marine Seismic Survey (MSS) Environment Plan. NOPSEMA invited Woodside to comment on draft conditions, granting a request to extend the submission deadline to 25 July 2023.…
-
NOPS
NOPSEMA
Date not published
F246-08
2 pages
PDF
NOPSEMA invited Woodside Energy to comment on draft conditions for the Scarborough 4D Multistring Subsea (MSS) Environmental Plan on July 13, 2023. The assessment had substantially progressed, and NOPSEMA requested Woodside's feedback on the proposed conditions by July 20, 2023.…
-
NOPS
NOPSEMA
Date not published
F246-07
3 pages
PDF
NOPSEMA invited Woodside Energy Scarborough Pty Ltd to comment on deficiencies identified in the resubmitted Environment Plan for the Scarborough 4D B1 Marine Seismic Survey. The regulator raised concerns about incomplete Indigenous consultation, specifically that consultation…
-
NOPS
NOPSEMA
Date not published
F246-06
2 pages
PDF
NOPSEMA responded to Woodside Energy's 4 July 2023 letter regarding consultation requirements under offshore petroleum regulations for the Scarborough Environment Plans assessment. The correspondence addresses Woodside's position on consulting with specified relevant persons and…
-
NOPS
NOPSEMA
Date not published
F246-05
2 pages
PDF
This email thread documents Woodside Energy's submission to NOPSEMA regarding the Scarborough environment plans assessment in July 2023. Woodside requested that NOPSEMA consider Woodside's response to the Environmental Defenders Office (dated 3 July 2023) when making regulatory…
-
NOPS
NOPSEMA
Date not published
F246-04
5 pages
PDF
Woodside Energy submitted correspondence to NOPSEMA on 4 July 2023 requesting that its response letter to the Environmental Defenders Office (dated 3 July 2023) be considered during NOPSEMA's assessment of multiple Scarborough environment plans. The four environment plans under…
-
NOPS
NOPSEMA
Date not published
F246-03
2 pages
PDF
On 22 June 2023, NOPSEMA notified Woodside Energy Scarborough Pty Ltd that it was unable to complete its assessment of the Scarborough 4D B1 Marine Seismic Survey environment plan within the standard 30-day review period. The operator had submitted the plan (Revision 7) on 2…
-
NOPS
NOPSEMA
Date not published
F246-02
2 pages
PDF
Woodside Energy submitted Revision 7 of its Scarborough 4D Multi-Sensor Seismic (MSS) Environment Plan to NOPSEMA on 12 June 2023. The submission corrected and updated several sections, including removal of non-adjacent Native Title claims and determinations from Table 4-17…
-
NOPS
NOPSEMA
Date not published
F246-01
11 pages
PDF
NOPSEMA rejected Woodside's environment plan for the Scarborough 4D B1 marine seismic survey because the plan inadequately described cultural heritage features and relied improperly on an independent heritage report commissioned by NOPSEMA rather than Woodside's own…